Systems engineering plan for the construction phase of the E-ELTFormat | Member Price | Non-Member Price |
---|---|---|
$17.00 | $21.00 |
Paper Abstract
After having completed the phase B (front-end design) of the several subsystems, the E-ELT project is entering into the
construction phase. The subsystems specifications, interface control documents and accompanying technical
documentation resulting from the said design activities are being drafted along with the statements of work needed for
the tendering processes.
This paper presents an overview of the Systems Engineering Plan for the construction phase focusing on the specific
systems engineering processes. The goal is to ensure that this phase is developed following an efficient systems
engineering approach based on the lessons learned during phase B. The ultimate objective is that the E-ELT meets the
science requirements defined by the users while the risk of overruns in cost or schedule, which might otherwise originate
from the lack of a system perspective, is minimized.
Paper Details
Date Published: 4 August 2014
PDF: 9 pages
Proc. SPIE 9150, Modeling, Systems Engineering, and Project Management for Astronomy VI, 91500U (4 August 2014); doi: 10.1117/12.2055188
Published in SPIE Proceedings Vol. 9150:
Modeling, Systems Engineering, and Project Management for Astronomy VI
George Z. Angeli; Philippe Dierickx, Editor(s)
PDF: 9 pages
Proc. SPIE 9150, Modeling, Systems Engineering, and Project Management for Astronomy VI, 91500U (4 August 2014); doi: 10.1117/12.2055188
Show Author Affiliations
J. C. Gonzalez, European Southern Observatory (Germany)
H. Kurlandczyk, European Southern Observatory (Germany)
H. Kurlandczyk, European Southern Observatory (Germany)
D. Schneller, European Southern Observatory (Germany)
Published in SPIE Proceedings Vol. 9150:
Modeling, Systems Engineering, and Project Management for Astronomy VI
George Z. Angeli; Philippe Dierickx, Editor(s)
© SPIE. Terms of Use