The aim of the Gemini Observatory’s Base Facilities Project is to provide the capabilities to perform routine night time operations with both telescopes and their instruments from their respective base facilities without anyone present at the summit. Tightening budget constraints prompted this project as both a means to save money and an opportunity to move toward increasing remote operations in the future.

We successfully moved Gemini North nighttime operation to our base facility in Hawaii in Nov., 2015. This is the first 8mclass telescope to completely move night time operations to base facility. We are currently working on implementing BFO to Gemini South.

Key challenges for this project include: (1) This is a schedule driven project. We have to implement the new capabilities by the end of 2015 for Gemini North and end of 2016 for Gemini South. (2) The resources are limited and shared with operations which has the higher priority than our project. (3) Managing parallel work within the project. (4) Testing, commissioning and introducing new tools to operational systems without adding significant disruptions to nightly operations. (5) Staff buying to the new operational model. (6) The staff involved in the project are spread on two locations separated by 10,000km, seven time zones away from each other. To overcome these challenges, we applied two principles: "Bare Minimum" and "Gradual Descent". As a result, we successfully completed the project ahead of schedule at Gemini North Telescope. I will discuss how we managed the cultural and human aspects of the project through these concepts. The other management aspects will be presented by Gustavo Arriagada [2], the Project Manager of this project. For technical details, please see presentations from Andrew Serio [3] and Martin Cordova [4].

Paper Details

Date Published: 9 August 2016
PDF: 8 pages
Proc. SPIE 9911, Modeling, Systems Engineering, and Project Management for Astronomy VI, 99111Q (9 August 2016); doi: 10.1117/12.2232084
Show Author Affiliations
Atsuko Nitta, Gemini Observatory (United States)
Gustavo Arriagada, Gemini Observatory (Chile)
A. J. Adamson, Gemini Observatory (United States)
Martin Cordova, Gemini Observatory (Chile)
Arturo Nunez, Gemini Observatory (Chile)
Andrew Serio, Gemini Observatory (Chile)
Scot Kleinman, Gemini Observatory (United States)


Published in SPIE Proceedings Vol. 9911:
Modeling, Systems Engineering, and Project Management for Astronomy VI
George Z. Angeli; Philippe Dierickx, Editor(s)

© SPIE. Terms of Use
Back to Top